University of Hull Framework 2018 to 2020

Client: The University of Hull

Value: £200m Capital Programme

Contract: NEC3 (various)

Services:

Cost Management

Contract Advice

The University of Hull, Consultants, Professional Services Framework, 2018 – 2020

We were appointed to the Cost Management Framework to support the University’s ambitious £200m capital works programme.

Projects delivered under the framework include:

  • New Engineering Building – RIBA 1 to 4 (£12m budget)
  • Unit 3F Refurbishment – RIBA 3 to 6 (£500k)
  • Westfield Court Refurbishment – RIBA 1 to 6 (£1m)
  • Media Hub (£1.5m)
  • EEI Ground Floor Refurbishment – RIBA 1 to 6 (£750k)
  • Water Main Diversion/Replacement – RIBA 3 to 6 (£350k)
  • EEI First Floor Refurbishment (£750k)
  • Laboratory Relocations (various)
  • Project ARK – development of brief, optioneering & business case RIBA 1 (civil engineering)

The above list includes completed and live projects.